UFRs

Unfunded Requirements (UFRs) are situations, services, or products that you cannot fund with your current Control. Work with your Regional Program Director (RPD) to develop a well-written, well-documented Unfunded Requirements Specification to ensure the best possible outcome of funding your UFRs.

Funding Sources

When searching for potential funding sources for a UFR, an Installation Program Manager (IPM) can leverage Commander, Navy Installations Command (CNIC) sources such as the:

  • Installation Program
  • Region Program
  • Region Comptroller (N8)
  • CNIC Comptroller (N8)
  • CNIC N9

Priority

Not all UFRS can be funded; therefore, UFRs are assigned a priority based on their necessity:

  • Priority 1 – Must Pay
  • Priority 2 – Mission Critical
  • Priority 3 – One-Time Efficiency
  • Priority 4 – Buy Ahead

Obligation Date

The date that funding must be obtained and supported by a procurement action or validated billet is:

  • Known as the latest obligation date
  • Determined by the IPM

Impact Statement

UFRs can impact your Program in various ways; determine:

  • If a UFR warrants submission to your RPD for possible funding. Then, make sure that you have a solid Impact Statement to accompany your submission
  • If any goods or services will be terminated if there is of a lack of funding; ensure they are included in your Impact Statement
An Impact Statement:
  • Describes what will be eliminated if the UFR is unfunded
  • Describes services or Programs that may be significantly reduced if unfunded
  • Cites negative customer impact
  • Indicates additional costs incurred by the customer or expenses to the Program

Justification Statement

A Justification Statement describes why the requirement is needed citing:

  • Policy
  • Mission
  • Common Output Level Standards (COLS)
  • Program Standards

Mitigation Plan

At times it may be necessary to adjust your Program's operations until funding is received. Before you implement a Mitigation Plan, ensure your Installation Commanding Officer (ICO) and RPD review and approve the plan. Consider a plan that:

  • Uses compensatory time and/or over-time
  • Detail personnel
  • Realign available Non-Labor funds to Labor
  • Contract for delivery of services
  • Uses funds in the Control already allocated to another purpose
  • Reduces services, Programs, or hours of operation

UFRs List

Keep a rolling list of all your prioritized UFRs. Purposes for keeping an updated prioritized list include:

  • Accurately reflects changes in customer needs
  • Reflects current Program requirements and mandates from higher authority
  • Enables the Program to meet COLS and Program Standards
  • Positions your Program to obtain funding for your UFRs when it is available